Populating a Project

Important note: as of October 2025 the Ftrack main navigation will be changing.  While we update our documentation to reflect this change, click here to learn more and orient yourself to the new layout.
Screenshot_2022-11-03_at_15.08.46.png

 

Via the Tasks Spreadsheet

To create a new object or task, right-click in the spreadsheet and select the preferred option from the Add menu.

This will contain all available objects that can be created on the particular entity your right-clicked on. 

Screenshot_2022-11-03_at_15.44.50.png

Choose the object you would like to create, and make sure to click the Save icon in the toolbar to save your work. 

Tips:

Populating a Task

While populating a Task, by default, the type of Tasks created is Generic, but depending on which Task types you have set up, you can change to any other task type that is available (modeling, animation, compositing etc.) 

Screenshot_2022-11-03_at_15.31.25.png

Once created, you can continue to set the values for your tasks, such as the bid, the start date, and due date, and assign users.

Via the Create dialog

You can also create objects like sequences, shots, and tasks by using the + Create dialog at the upper-left of the toolbar and selecting an option from the menu that appears.

Screenshot_2022-11-03_at_15.48.17.png

Once selected, it opens a new window where you can set the requested values.

Screenshot_2022-11-03_at_15.48.48.png

 

 